Construction
The specially adapted lorries are organised so that the timber frame panels required first are the most accessible and able to be lifted into place in sequence.
One of the many advantages of Climät-Hus is that rain-tight assembly can be achieved by the end of week 1 depending on your preferred roof covering.
The prefabricated structural components fit together effortlessly – the standard for a Swedish build!

![]()
Prior to erection team start on site
The ground floor slab was constructed and soleplates fixed and checked for dimensional accuracy in plenty of time prior to the date when the construction team arrive.
Full height independent scaffolding is erected to ensure safety of operatives. The scaffolding needs thought that it will not inhibit the placement of any of the panels.